The first 500 kV substation during the "14th Five-Year Plan" period in Sichuan Province

The first 500 kV substation during the "14th Five-Year Plan" period in Sichuan Province

  On June 10, the Sanqing Village, Wujia Town, Wucheng District, Mianyang City, with the two main transformer switches of 500 kV Song State substation impact, and operated in the network, marking the 54th 500 kV substation of Sichuan Power Grid Officially put it.

The substation is also the first 500 kV substation, which is put into operation during the "14th Five-Year Plan" period of Sichuan Province. The 500 kV-storey substation covers an area of ??acres and project investment is about 1 billion yuan, which is a key project project of the "14th Five-Year Plan" planning of Sichuan Power Grid.

After the station is shipped, 500 kV power supply double ring network will form a 500 kV power supply station, which greatly improves the main grid structure of the Sichuan Northern Power Grid, which has improved the reliability of power supply, effectively relieving Mianyang, Deyang Power Supply, Provide powerful power support for major scientific research industry projects in Mianyang Science and Technology City.

  Affected by the epidemic, since it started on April 18, 2020, the effective construction period of the project was only 12 months, and the construction period of the conventional 500 kV substation was 18 months.

National Network Sichuan Electric Power Company organizes all participating units to promote the prevention and control of the epidemic prevention and control, adhere to the planned non-conditioner, the task is not reduced, the target is unchanged, the continuous strengthening of engineering security, the quality of the whole process, strict attention nodes, grasp the key points , Hard-working, order to advance the work, and ensure that the "Template Project" of the "14th Five-Year Plan" opening of Sichuan Power Network has achieved "opening".

(Wang Zhiqi Liu Xiang Yun Yue Journalist Li Xinyi).